BCM completes “The Test” for Cielo Productions

Really proud to announce the completion of our latest project produced in partnership with Cielo Productions and Producer Gary Strieker. Medical textile company, Vestergaard Frandsen was looking for a special way to celebrate their 50th Anniversary. They didn’t just want to spend a lot of money on a party, a company trip, etc… They decided [...]

BCM_Construction_Day 88: Framing is completed!

Made our last payment on the framing today and all of the “quick and easy” work is now pretty much completed. The framing team did an amazing job and I’m very thankful for all their hard work. My buddy Jeanna and her family came by for the “skeleton tour.” A look into our kitchen / [...]

BCM Construction Day 87: Sound / Color Room appears!

Went in today to meet with the electrician and check out the framing on the “room within a room” in the Client Theater / Sound Design / Color Enhancement suite. Very cool! Looking at the back of the Client Theater. You can see how the inner wall pulls away from the outer wall. There’s [...]

BCM_Construction_Day 85: Bricks, Conference Room and Sound

It’s September 14th, and the bricks are about done, the Conference Room makes its first appearance and the “inner room” of the sound suite is starting to take shape. Standing in the kitchen looking at our roughly framed Conference Room. We designed it pretty darn big at about 12 feet wide and 20 feet long. [...]

BCM Construction Day 82: Bricks moving along

The speed that these guys are moving along with the brickwork is amazing. Then again, it’s just three straight runs that make their lives a lot easier. But I’m just so impressed with the quality of the craftsmanship going on that’s for sure. My nephew Quinn, Rebecca and my brother in law Randy stop by [...]

BCM expands DVD duplication capabilities

Thanks to a gentle push by one of our clients, we’ve invested in some new CD/DVD duplication equipment that has greatly enhanced our ability to turn around larger orders for clients. We added a Microboards 7 DVD burner giving us the capacity to burn around 500 to 600 DVDs in a single day! [...]

BCM Construction_Days 80 & 81: Bricks, framing and sound

Here’s a two day update on the goings on at our construction site. I have to say at this point it is getting a little bit overwhelming now that we can actually see all the rooms framed up and realize just how much more space we are moving in to. Our current space is [...]

BCM Construction_Day 79: Bricks and more bricks

John and I stopped by this afternoon to take a quick look at the progress on the bricks. Lower level is about done and they’re ready to get moving up on the scaffolding. Really loving the color scheme too. A look at the left side of the building around the garage door. That brick is [...]

BCM_Construction_Day 76: Brick laying starts

With the Labor Day Holiday weekend upon us, but an absolutely gorgeous day outside, the construction crew decided to work on Saturday and take Monday off. The brick work was started and Joe managed to get his truck in a ditch….. The masonry team gets right to work on the bricks outside. Joe brought us [...]

BCM_Construction_Day 74: Edit suites framed out

The gang and I stopped by to check on the construction. The work crew was on their lunch break so we had the place to ourselves. I’m in the conference room looking back across the facility. That’s Adrienne and Jenny standing just outside one of the bathrooms. These clears pan steel buildings are just so [...]